I am working in IWMPTEC-NICICO as project manager in SUNGUN mine:
RAW WATER
We designed raw water pump stations since 2 years ago for feeding the mine and now are close to commissioning these raw water pump stations are the highest pressure pump stations in Middle East.
Commissioning was done at 2013.12.03
PUMPS SUPPLIED FROM: KSB HGC TYPE
VALVES SUPPLIED FROM: FLOWROX

TAILING:
We are using the biggest centrifugal slurry pump station in the world and this station is under operation since 2005.
PUMPS SUPPLIED FROM: WEIR MINERALS WARMAN AH TYPE
VALVES SUPPLIED FROM: FLOWROX

RECLAIM WATER:
We are using some pontoon pump stations and return water pump stations.
PUMPS SUPPLIED FROM: APE SA VERTICAL TURBINE TYPE
VALVES SUPPLIED FROM: FLOWROX

PIPELINES:
More than 200 Km with many kind of sizes , steel lined and unlined and HDPE.

Career medium 06
Career
Career medium 04

Moshiran co

Equipment Installation Manager

I was the Equipment installation manager at PHASE one in SUNGUN mine ,actually MOSHIRAN CO was the main contractor for doing all the jobs in SUNGUN mine during PHASE one.